Question 1 PPL-001
You are the project manager of an agile software project. A developer has been blocked for two days waiting for the security team to review an API integration. The developer is frustrated and the sprint goal is at risk. What should you do first?
Question 2 PPL-004
You are kicking off a hybrid project with a mix of collocated and remote members, some new to agile. Before any delivery work begins, what should you establish first with the team?
Question 3 PPL-006
Your Scrum team has started skipping sprint retrospectives, saying "we know what went wrong already." Velocity has plateaued for three sprints. What should you do?
Question 4 PPL-009
Your hybrid team spans four time zones with only two hours of overlap. Misunderstandings are increasing and decisions made in chat threads are being missed. What is the most effective first action?
Question 5 PRC-001
Mid-execution, a key stakeholder requests a significant scope addition verbally in a hallway conversation, promising "we'll sort out the paperwork later." The addition would help the business. What should you do?
Question 6 PRC-004
Your hybrid project has a predictive phase gate for hardware and agile sprints for software. A software change affects a hardware interface specification. What should happen?
Question 7 PRC-006
Mid-sprint, the product owner learns of a market shift and wants to cancel the sprint. The team is 60% through the work. What is the correct agile guidance?
Question 8 PRC-007
A project baseline has been established. A team member proposes a better technical approach that would change the schedule baseline. What is the correct sequence?
Question 9 BE-002
You are a project manager in a functional organization. You need a specialist from another department for two weeks, but the functional manager refuses, citing their own priorities. What does this situation illustrate?
Question 10 BE-003
Mid-project, a new regulation requires all customer data to be stored domestically, invalidating your cloud architecture. This is a change in the external business environment. What should you do first?
Your result: /10
The full kit has 190 more questions like these, plus a 30-day study plan and EVM formula sheet.